CHANDLER BRIDGE CLOSED TWO WEEKENDS IN JUNE  
  
Coos River Highway (Oregon 241) will close at Chandler Bridge for two weekends in June due to a painting and repair project.  
  
The first 55-hour closure is scheduled to begin at 6 p.m. on Friday, June 12, and will continue until 1 a.m. on Monday, June 15. The second closure will follow the same hours, Friday night to Monday morning, June 19-22.  
  
During the closures, travelers from the east end of Coos River Highway can detour along East Bay Road and U.S. 101 to reach Coos Bay and North Bend.  
  
The highway closures will allow workers to paint sections of the bridge that are inaccessible when vehicles are moving along the travel lanes.  
  
Traffic across the bridge is currently limited to a single lane, with a temporary signal providing traffic control. Most delays are around five minutes or less.  
  
Minnesota-based Abhe & Svoboda, Inc., is the prime contractor on the $7.29 million project. All work is scheduled for completion in September.  
  
Chandler Bridge opened in 1952 and is located about three miles east of downtown Coos Bay. The paint on the truss is peeling and much of the steel is covered in rust.  
  
For more information, visit the project webpage or contact ODOT Public Information Officer Dan Latham at 541-817-5200.
CHANDLER BRIDGE CLOSED TWO WEEKENDS IN JUNE  
  
Coos River Highway (Oregon 241) will close at Chandler Bridge for two weekends in June due to a painting and repair project.  
  
The first 55-hour closure is scheduled to begin at 6 p.m. on Friday, June 12, and will continue until 1 a.m. on Monday, June 15. The second closure will follow the same hours, Friday night to Monday morning, June 19-22.  
  
During the closures, travelers from the east end of Coos River Highway can detour along East Bay Road and U.S. 101 to reach Coos Bay and North Bend.  
  
The highway closures will allow workers to paint sections of the bridge that are inaccessible when vehicles are moving along the travel lanes.  
  
Traffic across the bridge is currently limited to a single lane, with a temporary signal providing traffic control. Most delays are around five minutes or less.  
  
Minnesota-based Abhe & Svoboda, Inc., is the prime contractor on the $7.29 million project. All work is scheduled for completion in September.  
  
Chandler Bridge opened in 1952 and is located about three miles east of downtown Coos Bay. The paint on the truss is peeling and much of the steel is covered in rust.  
  
For more information, visit the project webpage or contact ODOT Public Information Officer Dan Latham at 541-817-5200.
CHANDLER BRIDGE CLOSED TWO WEEKENDS IN JUNE Coos River Highway (Oregon 241) will close at Chandler Bridge for two weekends in June due to a painting and repair project. The first 55-hour closure is scheduled to begin at 6 p.m. on Friday, June 12, and will continue until 1 a.m. on Monday, June 15. The second closure will follow the same hours, Friday night to Monday morning, June 19-22. During the closures, travelers from the east end of Coos River Highway can detour along East Bay Road and U.S. 101 to reach Coos Bay and North Bend. The highway closures will allow workers to paint sections of the bridge that are inaccessible when vehicles are moving along the travel lanes. Traffic across the bridge is currently limited to a single lane, with a temporary signal providing traffic control. Most delays are around five minutes or less. Minnesota-based Abhe & Svoboda, Inc., is the prime contractor on the $7.29 million project. All work is scheduled for completion in September. Chandler Bridge opened in 1952 and is located about three miles east of downtown Coos Bay. The paint on the truss is peeling and much of the steel is covered in rust. For more information, visit the project webpage or contact ODOT Public Information Officer Dan Latham at 541-817-5200.

Published on: 04/16/2026

This news was posted by City of Coos Bay

Go To Business Place

Description

CHANDLER BRIDGE CLOSED TWO WEEKENDS IN JUNE

Coos River Highway (Oregon 241) will close at Chandler Bridge for two weekends in June due to a painting and repair project.

The first 55-hour closure is scheduled to begin at 6 p.m. on Friday, June 12, and will continue until 1 a.m. on Monday, June 15. The second closure will follow the same hours, Friday night to Monday morning, June 19-22.

During the closures, travelers from the east end of Coos River Highway can detour along East Bay Road and U.S. 101 to reach Coos Bay and North Bend.

The highway closures will allow workers to paint sections of the bridge that are inaccessible when vehicles are moving along the travel lanes.

Traffic across the bridge is currently limited to a single lane, with a temporary signal providing traffic control. Most delays are around five minutes or less.

Minnesota-based Abhe & Svoboda, Inc., is the prime contractor on the $7.29 million project. All work is scheduled for completion in September.

Chandler Bridge opened in 1952 and is located about three miles east of downtown Coos Bay. The paint on the truss is peeling and much of the steel is covered in rust.

For more information, visit the project webpage or contact ODOT Public Information Officer Dan Latham at 541-817-5200.

669670262_1265596285729204_4419673007891

News Source : https://www.facebook.com/672903211665184/posts/1270888925199940

Other Related News

04/16/2026

The Portland Fire have added another guard to the roster with just days to go before train...

04/16/2026

One of the top executives in Samsungs contract manufacturing business is jumping to Intel

04/16/2026

The Oregon State Medical Examiners Office has identified remains from a car found in the C...

04/16/2026

The investigation into US Labor Secretary Lori Chavez-DeRemer has uncovered text messages ...

04/16/2026

People who were at Mt Hood Community College in Gresham earlier this week may have been ex...

ShoutoutGive Shoutout
500/500